POLICY: Buyout Schedule

PURPOSE: To ensure the buyout of the project is performed in a timely manner and supports the schedule.

RESPONSIBILITY: Project Manager

PROCEDURE:

1. Review the estimate for all items to be purchased by written purchase order and/or subcontract.

2. List each item to be purchased with its cost code, estimated cost, and delivery date onto the Buying Schedule. Include all materials, labor only subcontract, and conventional subcontracts. Items listed in the Buying Schedule should be arranged by CSI Divisions.

3. Buyout should progress in a timely manner and should complete not later than sixty (60) to ninety (90) days after budget approval.

4. The Buying Schedule will be set-up by the Project Manager.

5. It is the Project Manager’s responsibility to ensure buyout progresses in a logical manner that supports the project schedule.

6. The Project Manager provides the Senior Project Manager and Vice President of Construction a copy of the schedule on a weekly basis until buyout is completed. Additionally, status of the buyout schedule will be discussed during the month Superintendent/PM project meeting.

Blank Buyout Schedule

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment