The topic you requested could not be found.
Related topics are listed below.

4.9 Material Inventory

Section 4. Project Controls » 4.9 Material Inventory

POLICY: Material Inventory PURPOSE: To ensure all material procured directly by Carter & Carter via Purchase Order is quantified and complies with products specified in the Purchase Order upon delivery to the project site. RESPONSIBILITY: Superintendent/Project…

2.14 Jobsite Safety

Section 2. Project Start Up » 2.14 Jobsite Safety

POLICY: Jobsite Safety PURPOSE: To ensure a safe working environment for all persons employed and/or visiting a Carter & Carter jobsite and to comply with all applicable OSHA regulations. RESPONSIBILITY: Superintendent PROCEDURE: The Job Safety Plan will be…

5.1.2 Project Daily Log

Section 5. Quality Assurance & Quality Control » 5.1 Day to Day QA/QC Procedures » 5.1.2 Project Daily Log

POLICY: Project Daily Log PURPOSE: To document a detailed record of each project’s daily activities. RESPONSIBILITY: The Superintendent PROCEDURE: 1. On your computer or iOS device, use Procore to enter and generate the daily log. 2. In addition to the…

4.8 Tool Inventory Log

Section 4. Project Controls » 4.8 Tool Inventory Log

POLICY: Tool Inventory Log PURPOSE: To ensure accountability of all job purchased tools. RESPONSIBILITY: The Superintendent PROCEDURE: 1. All non-expendable tools, when purchased, shall be listed on the General Tool Inventory Log. 2. The inventory log shall be…

Section 4. Project Controls

Section 4. Project Controls

1.13 Drawing and Specification Log

Section 1. Pre-Construction » 1.13 Drawing and Specification Log

POLICY: Drawing and Specification Log PURPOSE: To provide a list of all drawings and specifications received and distributed. RESPONSIBILITY: Estimator in Charge PROCEDURE: A. All drawings and specifications received from the Owner or Architect will be listed…

2.4 Submittal & Material Lead Time Logs

Section 2. Project Start Up » 2.4 Submittal & Material Lead Time Logs

POLICY: Submittal and Material Lead Time Logs PURPOSE: To ensure the approval of submittals and the delivery of materials is performed in a timely manner and supports the schedule. RESPONSIBILITY: Project Manager PROCEDURE: 1. The following logs will be used…

4.4 Monthly Site Wide Safety Meetings

Section 4. Project Controls » 4.4 Monthly Site Wide Safety Meetings

POLICY: Monthly Site Safety Meetings PURPOSE: To educate and discuss jobsite safety concerns and issues. RESPONSIBILITY: The Superintendent PROCEDURE: 1. The meetings will be conducted monthly on a day and time selected by the Superintendent. The exact…

4.5 Mid-Month Project Status Meetings

Section 4. Project Controls » 4.5 Mid-Month Project Status Meetings

POLICY: Mid Month Project Status Meetings PURPOSE: The Project Manager, Superintendent and Senior Staff will meet as scheduled to review current project progress. PROCORE must be up to date for this meeting. This meeting should run no more than 1…

Section 2. Project Start Up

Section 2. Project Start Up

2.11 Mandatory Posting Requirements

Section 2. Project Start Up » 2.11 Mandatory Posting Requirements

POLICY: Mandatory Posting Requirements PURPOSE: To ensure compliance with all Federal and State posting requirements RESPONSIBILITY: Superintendent/Director of Administration PROCEDURE: The following documents must be displayed in a prominent location, i.e. field…

3.2 Vendor Purchase Order Agreement

Section 3. Project Administration » 3.2 Vendor Purchase Order Agreement

POLICY: Vendor Purchase Order Agreement PURPOSE: To establish a uniform procedure for the preparation of the purchasing agreements with vendors that supply only material to our projects. RESPONSIBILITY: Project Manager PROCEDURE: 1. The Project Manager will…

2.12 Site Logistics Plan

Section 2. Project Start Up » 2.12 Site Logistics Plan

POLICY: Site Logistics Plan PURPOSE: To ensure a plan is established for temporary facilities set up prior to mobilization. The plan will provide for storage, offices, traffic, signage, parking, utilities and other requirements and will be compatible with the…

3.1 Subcontract Agreement

Section 3. Project Administration » 3.1 Subcontract Agreement

POLICY: Subcontract Agreement PURPOSE: To have a written agreement, understanding, and commitment with individuals or companies providing labor or labor and materials to our projects. RESPONSIBILITY: Project Manager PROCEDURE: 1. The Project Manager will…

6.3 Owner’s Close Out Manual

Section 6. Project Closeout » 6.3 Owner’s Close Out Manual

POLICY: Owner’s Closeout Manual PURPOSE: To provide documentation relative to the project for proper operation, maintenance, and record keeping. RESPONSIBILITY: Project Manager NOTE: This file should be turned over to the Owner no later than thirty (30) days…

5.5.2 3rd Party Report Responses

Section 5. Quality Assurance & Quality Control » 5.5 Misc. QA/QC Procedures » 5.5.2 3rd Party Report Responses

POLICY: 3rd Party Report Responses PURPOSE: Ensure Carter & Carter quality standards are maintained by utilizing a standardized process for tracking and documenting the completion of 3rd party project reports. RESPONSIBILITY: Superintendent/Assistant Project…

4.1 Subcontractor Pre-Construction Start Up Meeting

Section 4. Project Controls » 4.1 Subcontractor Pre-Construction Start Up Meeting

POLICY: Subcontractor Pre-Construction Start Up Meeting PURPOSE: A meeting will be held with each individual Subcontractor to discuss key aspects of their scope of work including safety, day to day job site procedures, administrative and clerical procedures,…

4.14 Fire Alarm System Check Out

POLICY: Fire Alarm System Check Out PURPOSE: To ensure the proper operation of the fire alarm system through systematic inspection and check out. RESPONSIBILITY: Electrician/Fire Alarm Subcontractor PROCEDURE: The Superintendent will check to ensure the following…

3.5 Joint Check

Section 3. Project Administration » 3.5 Joint Check

POLICY: Joint Check PURPOSE: To ensure payment of all materials to lower tier suppliers. RESPONSIBILITY: Project Manager PROCEDURE: 1. The decision to utilize the Joint Check Agreement will be based on: Carter & Carter Construction Sub/Vendor qualification…

6.6 Warranty Procedure

Section 6. Project Closeout » 6.6 Warranty Procedure

POLICY: Warranty Procedure PURPOSE: To ensure all warranty issues are addressed and resolved in a timely manner. RESPONSIBILITY: Project Manager PROCEDURE: 1. Workmanship and defective material issues that occur after Carter & Carter demobilizes from the…

4.12 Anchor Bolt Layout

POLICY: Anchor Bolt Layout PURPOSE: To provide a consistent method for accurate placement and checking of anchor bolts. RESPONSIBILITY: The Concrete Subcontractor or Framer PROCEDURE: The Superintendent will ensure the following is completed and accurate. 1.…

4.6 Owner/Architect/Contractor Meeting (Monthly)

Section 4. Project Controls » 4.6 Owner/Architect/Contractor Meeting (Monthly)

POLICY: Owner/Architect/Contractor Meeting (Monthly) PURPOSE: Monthly meetings held by the Project Manager to review Project Status with the Owner and Architect. RESPONSIBILITY: Project Manager PROCEDURE: 1. The Project manager shall schedule a meeting monthly…

2.19 Project Bulletin Board

Section 2. Project Start Up » 2.19 Project Bulletin Board

POLICY: Project Bulletin Board PURPOSE: To satisfy posting regulations and to promote good communications. RESPONSIBILITY: Superintendent PROCEDURE: Each Carter & Carter Construction project will be equipped with an exterior bulletin board. The board will be…

4.13 Smoke/Fire Damper Check Out

POLICY: Smoke/Fire Damper Check Out PURPOSE: To ensure the proper operation of dampers through systematic inspection and check out. RESPONSIBILITY: HVAC Subcontractor/Foreman PROCEDURE: The Superintendent will check to ensure the following items have been…

6.2 Owner’s Project Closeout Meeting

Section 6. Project Closeout » 6.2 Owner’s Project Closeout Meeting

POLICY: Owner’s Project Closeout Meeting PURPOSE: To develop a plan and time line for completion of all open issues and contractual requirements necessary to receive final retainage payment. RESPONSIBILITY: Project Manager PROCEDURE: No later than (60) days…

5.1.5 Project Observations

Section 5. Quality Assurance & Quality Control » 5.1 Day to Day QA/QC Procedures » 5.1.5 Project Observations

POLICY: Procore Observation Tab PURPOSE: To ensure Carter & Carter safety and quality control standards are achieved and maintained to the highest level on each project site. RESPONSIBILITY: Carter & Carter Project Team PROCEDURE: Carter & Carter Construction…

2.9 Overall Project Schedule (OPS)

Section 2. Project Start Up » 2.9 Overall Project Schedule (OPS)

POLICY: Overall Project Schedule (OPS) PURPOSE: To ensure the entire plan for constructing the project is drafted into a bar chart format and confirmed by Carter & Carter and its subcontractors. RESPONSIBILITY: Project Manager, Superintendent PROCEDURE: An…

2.3 Buyout Schedule

Section 2. Project Start Up » 2.3 Buyout Schedule

POLICY: Buyout Schedule PURPOSE: To ensure the buyout of the project is performed in a timely manner and supports the schedule. RESPONSIBILITY: Project Manager PROCEDURE: 1. Review the estimate for all items to be purchased by written purchase order and/or…

4.2 Near Term Schedule

Section 4. Project Controls » 4.2 Near Term Schedule

POLICY: Near Term Schedule PURPOSE: To actively monitor, evaluate and update the progress of the project and plan the upcoming work activities. RESPONSIBILITY: The Superintendent PROCEDURE: 1. A Near Term Schedule will be prepared prior to beginning work on…

5.1.3 Weather Delays

Section 5. Quality Assurance & Quality Control » 5.1 Day to Day QA/QC Procedures » 5.1.3 Weather Delays

POLICY: Weather Delay Policy & Procedure PURPOSE: To document a detailed record of weather delay’s daily. PROCEDURE: RESPONSIBILITY: SUPERINTENDENT 1. Rain delays are documented daily through the Project Daily Reports under “Observed Weather Conditions” in…

5.2.2 Construction Mock Up

Section 5. Quality Assurance & Quality Control » 5.2 Sitework & Exterior QA/QC » 5.2.2 Construction Mock Up

POLICY: Construction Mock Up PURPOSE: 1. To ensure all exterior finish materials have been furnished and installed in conformance with approved material selections and; 2. To ensure all exterior and waterproofing components are installed to acceptable workmanship…

2.7 Subcontractor Qualification

Section 2. Project Start Up » 2.7 Subcontractor Qualification

POLICY: Subcontractor Qualification PURPOSE: To ensure quality subcontractors who are capable of performing the specified scope of work are contracted. RESPONSIBILITY: Project Manager PROCEDURE: Upon solicitation for bid, Subcontractors will be emailed a link…

1.18 Estimate Presentation

Section 1. Pre-Construction » 1.18 Estimate Presentation

POLICY: Estimate Presentation PURPOSE: To present the estimated cost of the project for owner approval. RESPONSIBILITY: Estimator in Charge PROCEDURE: 1. After the Estimate is complete, a minimum of two days prior to presentation to the Approving Authority, the…

5.1.4 Daily Photos

Section 5. Quality Assurance & Quality Control » 5.1 Day to Day QA/QC Procedures » 5.1.4 Daily Photos

POLICY: Daily Photos PURPOSE: To ensure day to day site conditions, critical components of construction, aesthetic features, safety and workmanship issues, etc. are thoroughly and appropriately documented. RESPONSIBILITY: Carter & Carter Project Teams PROCEDURE:…

5.4.4 Unit Lock Up

Section 5. Quality Assurance & Quality Control » 5.4 Finishes QA/QC » 5.4.4 Unit Lock Up

POLICY: Unit Lock Up PURPOSE: To ensure finished units are adequately protected from damage, vandalism, and material theft. RESPONSIBILITY: The Superintendent PROCEDURE: Upon installation of appliances in units, Carter & Carter Superintendent shall designate an…

2.10 C&C Internal Pre-Construction Conference

Section 2. Project Start Up » 2.10 C&C Internal Pre-Construction Conference

POLICY: Carter & Carter Team Internal Pre-Construction Conference PURPOSE: To provide a formal status report to the members of the Carter & Carter Construction Team at the beginning of each project. RESPONSIBILITY: Project Manager PROCEDURE: 1. Prior to actual…

1.17 Projected Cash Flow Chart

Section 1. Pre-Construction » 1.17 Projected Cash Flow Chart

POLICY: Projected Cash Flow Chart PURPOSE: To advise the owner of the project’s projected cash flow. RESPONSIBILITY: Project Manager PROCEDURE: If required, a Projected Cash Flow Chart will be prepared by the Project manager providing the data requested…

6.1 Project Close-Out Action List

Section 6. Project Closeout » 6.1 Project Close-Out Action List

POLICY: Project Close-Out Action List PURPOSE: To ensure all costs are accounted for and that Carter & Carter will not encounter any liability after the job is closed out. RESPONSIBILITY: Project Manager PROCEDURE: The Project Manager is to ensure that all bills…

1.14 Subcontractor/Vendor Worksheets

Section 1. Pre-Construction » 1.14 Subcontractor/Vendor Worksheets

POLICY: Subcontractor/Vendor Worksheets PURPOSE: To use as a worksheet for recording bidding data. RESPONSIBILITY: Estimator in Charge PROCEDURE: A. The company name of all subcontractors and vendors who are bidding or who have been contacted for bids will…

4.16 Conversation Notes

POLICY: Conversation Notes PURPOSE: To document specific conversations for future reference. RESPONSIBILITY: The Originator PROCEDURE: A Conversation Note will be used when documentation and/or future action is required after a specific conversation. 1. All…

5.2.4 Exterior Finish Punch

Section 5. Quality Assurance & Quality Control » 5.2 Sitework & Exterior QA/QC » 5.2.4 Exterior Finish Punch

POLICY: Exterior Finish Punch PURPOSE: Ensure Carter & Carter quality standards are maintained by generating a concise and organized list of Exterior Punch items and track their satisfactory completion. RESPONSIBILITY: Exteriors Assistant Superintendent PROCEDURE:…

2.17 Out of Town Expense/Living Allowance Reimbursement

Section 2. Project Start Up » 2.17 Out of Town Expense/Living Allowance Reimbursement

POLICY: Out of Town Expense/Living Allowance Reimbursement PURPOSE: To maintain a standard policy for the reimbursement of out of town expenses for supervisors assigned to projects more than 60 miles from the corporate office. RESPONSIBILITY: Senior Project…

1.19 Estimate Transfer from Timberline Estimating to Timberline Accounting

Section 1. Pre-Construction » 1.19 Estimate Transfer from Timberline Estimating to Timberline Accounting

POLICY: Estimate Transfer from Timberline Estimating to Timberline Accounting PURPOSE: To manage the transfer of cost codes and related budget amounts from estimating into accounting. RESPONSIBILITY: Estimator in Charge PROCEDURE: After a formal notice is given…

2.13 Field Office Layout and Setup

Section 2. Project Start Up » 2.13 Field Office Layout and Setup

POLICY: Field Office Layout and Setup PURPOSE: To ensure a plan is established for the selection and delivery of field offices and furnishings that are consistent throughout the company, functional and compatible with the estimate. RESPONSIBILITY: Superintendent …

6.3 Sub/Vendor Warranties

Section 6. Project Closeout » 6.3 Sub/Vendor Warranties

POLICY: Sub/Vendor Warranties PURPOSE: To ensure the subcontractors and vendors understand and commit to warrant their work as specified. RESPONSIBILITY: Project Manager PROCEDURE: 1. Before retainage is released to a subcontractor, a written warranty matching…

3.4.2 Contractors Application for Payment

Section 3. Project Administration » 3.4 Pay Application Processes » 3.4.2 Contractors Application for Payment

POLICY: (External) Contractors Application for Payment PURPOSE: To provide the Owner with a concise and consistent billing. RESPONSIBILITY: Project Manager PROCEDURE: 1. The contract is to be reviewed to determine when billings are to be submitted. Typical…

3.4.3 Internal Subcontractor & Owner Pay Application Process

Section 3. Project Administration » 3.4 Pay Application Processes » 3.4.3 Internal Subcontractor & Owner Pay Application Process

POLICY: Internal Subcontractor & Owner Pay Application Process PURPOSE: To ensure both C&C and Subcontractors are paid timely and accurately. RESPONSIBILITY: Project Manager/Construction Administration PROCEDURE: Subcontractor/Vendor Pay Applications 1. On…

5.4.3 Owner’s Punch

Section 5. Quality Assurance & Quality Control » 5.4 Finishes QA/QC » 5.4.3 Owner’s Punch

POLICY: Owner’s Punch PURPOSE: Ensure Carter & Carter quality standards are maintained by generating a concise and organized list of Owner’s Punch items and track their satisfactory completion. RESPONSIBILITY: Finishes Assistant…

2.14.1 Reporting Injuries

Section 2. Project Start Up » 2.14 Jobsite Safety » 2.14.1 Reporting Injuries

POLICY: Reporting Injuries PURPOSE: To establish a uniform procedure for reporting injuries. RESPONSIBILITY: Superintendent PROCEDURE: If an injury occurs: 1.Obtain appropriate medical treatment. 2. Contact the corporate office and report the injury to the…

1.1 Preliminary Conceptual Estimate

Section 1. Pre-Construction » 1.1 Preliminary Conceptual Estimate

POLICY: Preliminary Conceptual Estimate PURPOSE: To ensure the consistent and thorough preparation and presentation of conceptual estimates. “Conceptual Estimating” is defined as the process of developing an estimate for a project based on a concept or…

5.3.1 Owner Box Walk

Section 5. Quality Assurance & Quality Control » 5.3 Vertical Construction & Pre-Finishes QA/QC » 5.3.1 Owner Box Walk

POLICY: Owner Box Walk PURPOSE: 1. To ensure all finish MEP components are installed in accordance with project documents and; 2. Identify conditions that may not be aesthetically acceptable to the owner and/or where installation of MEP components may be…

1.20 Historical Data

Section 1. Pre-Construction » 1.20 Historical Data

POLICY: Historical Data PURPOSE: To gather and maintain historical information for all completed projects. This will include the Project Cost History as well as the Quantity History. RESPONSIBILITY: Chief Estimator PROCEDURE: 1. After a project is completely…

4.17 Punch Out

POLICY: Punch Out/Inspection for Subcontractors PURPOSE: To provide for the orderly assignment of uncompleted work items and track their satisfactory completion. RESPONSIBILITY: Superintendent PROCEDURE: Inspections will be performed as described at the following…

2.6 Schedule of Values and Cost Codes

Section 2. Project Start Up » 2.6 Schedule of Values and Cost Codes

POLICY: Schedule of Values and Cost Codes PURPOSE: To provide an itemized list of construction activities along with their respective value to establish an accurate basis of payment. RESPONSIBILITY: Project Manager PROCEDURE: 1. Review the construction…

1.10 Public Bid Room Notification

Section 1. Pre-Construction » 1.10 Public Bid Room Notification

POLICY: Public Bid Room Notification PURPOSE: To provide broad public notification of bidding information pertaining to the project. RESPONSIBILITY: Estimator in Charge PROCEDURE: Notify the Dodge Rooms or Builders Exchanges (sample memo attached) in the…

5.3.2 Framing Punch

Section 5. Quality Assurance & Quality Control » 5.3 Vertical Construction & Pre-Finishes QA/QC » 5.3.2 Framing Punch

PURPOSE: To generate a concise and organized list of uncompleted framing items and track their satisfactory completion. RESPONSIBILITY: Framing Assistant Superintendent PROCEDURE: Inspections will be performed as described on all Carter & Carter Construction…

3.8 Projected Cost Update

Section 3. Project Administration » 3.8 Projected Cost Update

POLICY: Projected Cost Update PURPOSE: To report the current cost status of the project and the anticipated final cost based on the best judgment of the management team. RESPONSIBILITY: Project Manager PROCEDURE: The anticipated final cost is an estimated number…

2.15 Drug and Alcohol Program

Section 2. Project Start Up » 2.15 Drug and Alcohol Program

POLICY: Drug and Alcohol Program PURPOSE: To provide guidelines for implementing the company drug and alcohol policy. A copy of the company drug and alcohol policy found in the employee handbook is attached. RESPONSIBILITY: Director of Administration PROCEDURE:…

2.1 Project Start Up Action List

Section 2. Project Start Up » 2.1 Project Start Up Action List

POLICY: Project Start Up Action List PURPOSE: To provide a check list of typical/critical items that will ensure proper project start-up. RESPONSIBILITY: Project Manager PROCEDURE: 1. The Project Manager will obtain a copy of the Carter & Carter Project…

2.5 Subcontractor Insurance Certificate

Section 2. Project Start Up » 2.5 Subcontractor Insurance Certificate

POLICY: Subcontractor Insurance Certificate PURPOSE: To have adequate insurance coverage. RESPONSIBILITY: Project Manager PROCEDURE: 1. An insurance certificate will be received from each subcontractor prior to his starting any work. No subcontractor shall be…

5.1.1 Daily Clean Up

Section 5. Quality Assurance & Quality Control » 5.1 Day to Day QA/QC Procedures » 5.1.1 Daily Clean Up

POLICY: Daily Clean Up PURPOSE: To ensure a safe working environment for all persons employed and/or visiting a Carter & Carter Construction jobsite and to improve efficiency through discipline and organization. RESPONSIBILITY: The Superintendent PROCEDURE:…

5.4.2 Carter & Carter Punch

Section 5. Quality Assurance & Quality Control » 5.4 Finishes QA/QC » 5.4.2 Carter & Carter Punch

POLICY: Carter & Carter Punch PURPOSE: Ensure Carter & Carter quality standards are maintained by generating a concise and organized list of Owner’s Punch items and track their satisfactory completion. RESPONSIBILITY: Finishes Assistant…

1.9 Bidder Information Sheet

Section 1. Pre-Construction » 1.9 Bidder Information Sheet

POLICY: Bidder Information Sheet PURPOSE: To Pre-qualify Bidders for Future Projects. RESPONSIBILITY: Estimator in Charge PROCEDURE: 1. A copy of the Bidder Information Sheet (Form O.EST.-50) will be mailed, emailed, or faxed to a prospective bidder as an…

5.3.3 MEP In Wall Punch

Section 5. Quality Assurance & Quality Control » 5.3 Vertical Construction & Pre-Finishes QA/QC » 5.3.3 MEP In Wall Punch

PURPOSE: To generate a concise and organized list of incomplete MEP Rough In items and track their satisfactory completion. RESPONSIBILITY: MEP Assistant Superintendent PROCEDURE: Inspections will be performed as described on all Carter & Carter Construction…

1.11 Estimating & Job Number/Cost Code

Section 1. Pre-Construction » 1.11 Estimating & Job Number/Cost Code

POLICY: Estimating & Job Number/Cost Code PURPOSE: To ensure continuity in the issuance of estimate numbers, job numbers, and cost codes. RESPONSIBILITY: Estimator in Charge PROCEDURE: Job numbers, estimate numbers, and cost codes shall be assigned by the…

3.4.1 Subcontractor Application for Payment and Partial Release of Lien

Section 3. Project Administration » 3.4 Pay Application Processes » 3.4.1 Subcontractor Application for Payment and Partial Release of Lien

POLICY: Subcontractor Application for Payment and Partial Release of Lien PURPOSE: To ensure a uniform billing procedure to subcontractors. RESPONSIBILITY: Project Manager PROCEDURE: 1. Subcontractor pay applications should be submitted on the day of the…

3.3 Change Order to Subcontractors and Purchase Orders

Section 3. Project Administration » 3.3 Change Order to Subcontractors and Purchase Orders

POLICY: Change Order to Subcontractors and Purchase Orders PURPOSE: To have a formal agreement to address revisions to the original Subcontracts and Purchase Orders. RESPONSIBILITY: Project Manager PROCEDURE: 1. Any potential change in price or a scope of work…

4.3 Weekly Subcontractor’s Scheduling Meeting

Section 4. Project Controls » 4.3 Weekly Subcontractor’s Scheduling Meeting

POLICY: Weekly Subcontractor’s Scheduling Meeting PURPOSE: To address and resolve daily problems and coordinate the work activities for the coming week. RESPONSIBILITY: The Superintendent PROCEDURE: 1. A formal meeting will be held each Tuesday at 9:00 AM…

5.2.1 Layout and Field Engineering

Section 5. Quality Assurance & Quality Control » 5.2 Sitework & Exterior QA/QC » 5.2.1 Layout and Field Engineering

POLICY: Layout and Field Engineering PURPOSE: To ensure the building and its components are positioned per the contract documents. RESPONSIBILITY: The Superintendent PROCEDURE: 1. The following are minimum items to be located and established by a licensed land…

1.12 The Estimate

Section 1. Pre-Construction » 1.12 The Estimate

POLICY: The Estimate PURPOSE: To establish the estimated cost of a project based on final plans and specifications. RESPONSIBILITY: Estimator in Charge PROCEDURE: To provide a final estimate using the following procedures: A. The Estimator/Project Manager…

3.7 Providing Proper Notice to a Subcontractor or Vendor

Section 3. Project Administration » 3.7 Providing Proper Notice to a Subcontractor or Vendor

POLICY: Providing Proper Notice to a Subcontractor or Vendor PURPOSE: To provide for methodical and orderly effort in which a subcontractor or vendor is legally notified to address contractual deficiencies and/or to be terminated. RESPONSIBILITY: Project Manager…

6.9 Post Project Summation Meeting

Section 6. Project Closeout » 6.9 Post Project Summation Meeting

POLICY: Post Project Summation Meeting PURPOSE: To review, discuss, and critique the project after completion and demobilization. RESPONSIBILITY: Project Manager PROCEDURE: 1. The Project Manager will establish the meeting date with the “Team” and…

6.5 Operation/Maintenance Documentation

Section 6. Project Closeout » 6.5 Operation/Maintenance Documentation

POLICY: Operation/Maintenance Documentation PURPOSE: To provide the Owner with all the information needed to properly operate and maintain the new facilities. RESPONSIBILITY: Project Manager PROCEDURE: 1. In accordance with the Contract Documents, provide all…

6.4 Subcontractor and Vendor Waiver & Release of Lien

Section 6. Project Closeout » 6.4 Subcontractor and Vendor Waiver & Release of Lien

POLICY: Subcontractor and Vendor Waiver & Release of Lien PURPOSE: To require proper release of lien from all subcontractors and vendors. RESPONSIBILITY: Project Manager PROCEDURE: 1. Before final retainage is released on a subcontractor, a final Release of…

2.16 Project Roles and Responsibilities

Section 2. Project Start Up » 2.16 Project Roles and Responsibilities

POLICY: Project Roles and Responsibilities PURPOSE: To assign specific responsibilities and establish a chain of command for each individual project. RESPONSIBILITY: Vice President of Operations PROCEDURE: 1. After a contract or a firm commitment has been made…

4.28 Project Assignments

POLICY: Project Assignments PURPOSE: To assign specific individual responsibilities and confirm the chain of command for each individual phase of the project. RESPONSIBILITY: Project Superintendent/Project Manager PROCEDURE: 1. After the project start-up, an…

6.8 Client Satisfaction Survey

Section 6. Project Closeout » 6.8 Client Satisfaction Survey

POLICY: Client Satisfaction Survey PURPOSE: To gather information from clients regarding Carter & Carter’s project performance so that Carter & Carter can improve future performance. RESPONSIBILITY: Project Manager PROCEDURE: 1. Upon project completion,…

1.3 Estimating Dropbox Folders

Section 1. Pre-Construction » 1.3 Estimating Dropbox Folders

POLICY: Estimating Dropbox Folder Setup PURPOSE: To ensure the orderly filing and cataloging of information throughout the estimating process. RESPONSIBILITY: Estimator in Charge PROCEDURE: To create a new project in dropbox go to Carter & Carter/1.…

1.8 Invitation to Bid

Section 1. Pre-Construction » 1.8 Invitation to Bid

POLICY: Invitation to Bid PURPOSE: To solicit bidders and establish pricing conditions for the project. RESPONSIBILITY: Estimator in Charge PROCEDURE: 1. An Invitations to Bid is to be sent to all bidders that wish to qualify to bid on the project or that are…

2.18 Internet Service Provider Setup

Section 2. Project Start Up » 2.18 Internet Service Provider Setup

POLICY: Internet Service Provider Setup PURPOSE: To provide a method to set up internet service accounts at the jobsite. RESPONSIBILITY: Project Manager PROCEDURE: 1. The Project Manager will investigate the availability of internet service providers (ISP) at…

4.7 Drawing/Document/As-Built Maintenance

Section 4. Project Controls » 4.7 Drawing/Document/As-Built Maintenance

POLICY: Drawing/Document/As-Built Maintenance PURPOSE: To ensure a complete set of the Contract Documents – drawings, specifications, addenda, change orders or other pertinent contract document information is current, on-site and available at all times for…

1.4 Preliminary Overall Project Schedule

Section 1. Pre-Construction » 1.4 Preliminary Overall Project Schedule

POLICY: Preliminary Overall Project Schedule PURPOSE: To ensure the entire plan for constructing the project is drafted into a bar chart format to be used (1) during the estimating phase to convey durations to subcontractors and vendors and (2) as part of the bid…