POLICY: Extra Work Authorization

PURPOSE: To establish a proper procedure for authorizing additional work.

RESPONSIBILITY: Superintendent

PROCEDURE: Additional work will only be authorized through the issuance of a formal Change Order (O.P.M.-40). If an immediate change is required at the jobsite level, a Field Memorandum will be issued to the subcontractor or vendor outlining the scope and the agreed-on price. The Field Memorandum will be forwarded to the Project Manager and used for back up when the actual Change Order is issued.

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.