Upon notification by responsible company project management or superintendents, the company Safety and Health Manager or a Project Manager will advise outside sub vendors in writing of:
- Any chemical hazards that may be encountered in the normal course of their work on the respective jobsite,
- The labeling system in use for hazardous materials,
- The protective measures to be taken by all sub vendor employees,
- The safe handling requirements and procedures to be used, and
- The location and availability of all Safety Data Sheets (SDSs).
Each separate contractor or subcontractor bringing any chemical on-site must provide Carter & Carter with their own contractor-specific HAZ-COM manual containing appropriate hazard information on all substances, including the labels used and the precautionary measures to be taken in working with these chemicals, and all necessary SDSs. All subcontractor HAZ-COM manuals will be stored on-site alongside the Carter & Carter HAZ-COM manual
Post your comment on this topic.