POLICY: Providing Proper Notice to a Subcontractor or Vendor

PURPOSE: To provide for methodical and orderly effort in which a subcontractor or vendor is legally notified to address contractual deficiencies and/or to be terminated.

RESPONSIBILITY: Project Manager and Superintendent

PROCEDURE: Subcontractors and vendors are legally bound by the agreements outlined in the executed Subcontracts and Purchase Orders with Carter & Carter. Carter & Carter is also bound to certain responsibilities by virtue of the same agreements. It is therefore critical that the Project Manager in conjunction with that Superintendent ensure that Carter & Carter upholds their end of the agreement. When the Subcontractor or Vendor materially defaults on their agreement or otherwise fails to uphold their part of the agreement, steps must be taken in order to bring the Subcontractor or Vendor into compliance and/or lay the groundwork for the ultimate termination of the agreement between the Subcontractor/Vendor and Carter & Carter.

Step # 1
Determine the exact part of the Subcontract or P.O. that involves the failure or default.

Step # 2
Consult with the Senior Project Manager or Executive in Charge to discuss and confirm the failure or default. This step should not be avoided as it is critical for the appropriate Carter & Carter personnel to understand the actions and risks.

Step # 3
Prepare a “Written Notice” to the Subcontractor or Vendor using Procore’s Forms Tab. Certain situations may require some deviations from the sample; however, it is critical that you note the Subcontractor’s Representative the is listed in the Subcontract Agreement.

It is important to monitor potential problems closely because the subcontract agreement requires seven (7) days written notice prior to termination. The P.O. can be cancelled at any time however, it is wise to provide seven (7) days notice.

NOTE: If the consequence is to terminate or replace the Subcontractor, the back up plan for having the work done should be outlined and agreed to by Senior Project Manager. Management of this act is critical to avoid potential unforeseen costs and loss of profits and time against the schedule.

Step # 4
Once the “Written Notice” is prepared and approved it should be delivered to the Subcontractor’s or Vendor’s Representative via Procore Form’s Tab. If the Subcontractor or Vendor is bonded, a copy should also be sent to the bonding company.

Step # 5
During the period of notification, the actions and progress of the Subcontractor / Vendor should be closely monitored and documented. At the end of the notification period a determination should be made in conjunction with the Senior Project Manager as to the response made by the Subcontractor / Vendor. The Subcontractor / Vendor can remain on notice and in default of the Subcontract / P.O. while being allowed to work on the project. This should be documented similar to the attached memo. Any correspondence from the subcontractor / vendor concerning the default must be answered in writing by Carter & Carter promptly.

Step # 6
If at the end of the period of notification it is determined that the Subcontractor / Vendor has not made sufficient efforts to overcome the deficiency and remains a larger risk to the project if allowed to keep working, the Subcontractor / Vendor should be terminated. This step could ultimately end in legal proceedings such as arbitration and extreme monetary claims for damages by the party being terminated and should not be taken lightly or without consultation with Carter & Carter Senior Management and legal counsel. If at the end of the seven days period a determination is made that the subcontractor / vendor has cured the default and later, because of new circumstances again becomes in default, the above noted steps must be followed again.

Step # 7
Once terminated, no additional payments should be made to the terminated party until the project is complete or until the reason for the notice of termination is resolved. A detailed record of all completion costs, including Carter & Carter Management time and expenses should be kept. Per the Carter & Carter Subcontract and Purchase Order the terminated party is responsible for the completion costs. If the ultimate completion costs are less than the amount remaining against the Subcontract or P.O., then the terminated party is due the remaining difference between the Subcontract and the amount paid to complete the work. If the ultimate completion costs are more than the Subcontract or P.O. had remaining, then the excess costs are due to Carter & Carter from this subcontractor / vendor.

GENERAL NOTES: As previously stated, the Senior Project Manager and Executive in Charge must be kept informed once it is thought a Subcontractor / Vendor must be put on “notice” or terminated. There are many combinations of logistical and legal issues that can occur once these steps are taken and each case must be evaluated independently to ensure the risk to Carter & Carter and the project is minimized and the situation is handled prudently.

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment