POLICY: Carter & Carter Completion List

PURPOSE: Ensure Carter & Carter quality standards are maintained by completing Carter & Carter’s internal unit completion list prior to Owner’s Punch.

RESPONSIBILITY: Finishes Assistant Superintendent

PROCEDURE: After substantial completion of each unit (all finishes are installed), Carter and Carter Finish Superintendent shall confirm each unit is ready for Carter & Carter internal punch by ensuring all items on the attached list are complete. It should take no more than five (5) days per floor or building section to complete this list.