PURPOSE: To generate a concise and organized list of uncompleted framing items and track their satisfactory completion.
RESPONSIBILITY: Framing Assistant Superintendent
PROCEDURE: Inspections will be performed as described on all Carter & Carter Construction projects:
1. The Framing Punch template form generated in Procore by the Assistant Project Manager or Field Engineer will be used. One form will be completed for each unit.
2. Generation of this punch list by the Framing Superintendent shall commence on each floor after removal of bracing at each floor, prior to any MEP rough-ins beginning.
3. Once the framing punch list at each floor is generated, the Assistant Project Manager shall distribute to the Framing Subcontractor via Procore. Framing subcontractor shall have forty eight hours (48) to complete its punch list at each floor.
4. Punch documentation will be stored in the Procore “Punch” tab.
**See attached example framing punch list
Framing Punch Example
**Framing Superintendent shall also use attached general framing checklist for general guidance as necessary.
Framing Checklist
Post your comment on this topic.