POLICY: Subcontractor Qualification
PURPOSE: To ensure quality subcontractors who are capable of performing the specified scope of work are contracted.
RESPONSIBILITY: Project Manager
PROCEDURE:
1. Prior to issuing a contract, the Project Manager is to review the subcontractor’s Bidder Information Sheet.
2. If the Project Manager is not familiar enough with the company to make a knowledgeable judgment on their competence to effectively perform the work, a Subcontractor Reference will be completed in accordance with Policy O.EST.-115.