POLICY: Construction Mock Up

PURPOSE:
1. To ensure all exterior finish materials have been furnished and installed in conformance with approved material selections and;
2. To ensure all exterior and waterproofing components are installed to acceptable workmanship standards in accordance with Project Documents, Design Team recommendations, and Water Intrusion Consultant recommendations (when applicable).

RESPONSIBILITY: The Superintendent

PROCEDURE: Prior to the start of vertical construction, Carter & Carter shall construct an exterior mock up in accordance with drawings provided by the Architect. Mock up shall include a scaled version of all building finish components applicable to the project for review and approval by the Owner and Design Team. Components shall typically include but not be limited to the following:

  • Concrete Slab
  • Wood framing
  • Waterproofing materials
  • Applicable Roofing materials/Aspalt shingles
  • Window
  • Exterior cladding (Hardie siding, stone, brick, etc.)
  • Paint
  • Trim/coping/flashing

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment