POLICY: Material Inventory

PURPOSE: To ensure all material procured directly by Carter & Carter via Purchase Order is quantified and complies with products specified in the Purchase Order upon delivery to the project site.

RESPONSIBILITY: Superintendent/Project Manager

PROCEDURE:

1. The following list includes, but is not limited to materials typically procured via Carter & Carter purchase order:

  • Lumber/exterior waterproofing materials
  • Structural Hardware
  • Trusses
  • Windows
  • Hardie Siding
  • Appliances

2. The Superintendent will designate on site C&C personnel to receive and inventory purchase order material immediately upon delivery.

3. Upon each material delivery, C&C personnel shall verify:

  • receipt of exact quantities listed on the bill of laden
  • material delivered complies with material specified within the Purchase Order agreement
  • condition of delivered material to ensure no damages have occurred prior to Carter & Carter receiving

4. Any discrepancies between quantities indicated on the bill of laden and quantities actually delivered shall be marked up directly on the ticket.

5. Designated C&C personnel will document on the delivery ticket and refuse delivery of any incorrect and/or damaged material.

6. Designated personnel shall not sign the delivery ticket until discrepancies are noted and photo documentation has occurred.

7. Photo documentation of quantity deficiencies, material irregularities, and/or damaged materials should be sent to the Project Manager immediately.

8. No C&C personnel shall sign for subcontractor material deliveries or any other third party deliveries under any circumstances.

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment