PURPOSE: To generate a concise and organized list of incomplete MEP Rough In items and track their satisfactory completion.

RESPONSIBILITY: MEP Assistant Superintendent

PROCEDURE: Inspections will be performed as described on all Carter & Carter Construction projects:

1. The MEP Punch template form generated in Procore by the Assistant Project Manager or Field Engineer will be used. One form will be completed for each unit.
2. Generation of this punch list by the MEP Superintendent shall commence after MEP rough ins are complete on each floor but prior to installation of drywall. Care should be taken to ensure all framing repairs caused by MP&E rough-ins and furr down installation is complete.
3. Once the MEP punch list at each floor is generated, the Assistant Project Manager shall distribute to all applicable MEP Subcontractors via Procore. Each Subcontractor shall have forty eight hours (48) to complete its punch list at each floor.
4. Punch documentation will be stored in the Procore “Punch” tab.

**See attached example MEP Rough In punch list
MEP In Wall Rough In Punch List

**MEP Superintendent shall also use attached general MEP Rough In checklist for general guidance as necessary.
MEP Checklist

Feedback

Was this helpful?

Yes No
You indicated this topic was not helpful to you ...
Could you please leave a comment telling us why? Thank you!
Thanks for your feedback.

Post your comment on this topic.

Post Comment