POLICY: Path to Water/Sanitary

PURPOSE: Establish a written process of required steps to attain permanent water/sanitary for each building.

RESPONSIBILITY: Superintendent

PROCEDURE: The following activities should be thoroughly planned/coordinated to ensure that water and sanitary connection to the building is sequenced within the project schedule to avoid potential critical path delays:

  1. Coordinate with owner and utility provider to ensure required water and sewer accounts are set up and fees are paid (tap, sewer impact, etc).
  2. Superintendent shall coordinate with local jurisdiction having authority (AHJ) to clearly understand all jurisdictional requirements to release water/sewer. (Camera & testing, bacteria, etc)
  3. Plumbing fixtures topped out and inspections passed.