POLICY: Path to Water/Sanitary
PURPOSE: Establish a written process of required steps to attain permanent water/sanitary for each building.
RESPONSIBILITY: Superintendent
PROCEDURE: The following activities should be thoroughly planned/coordinated to ensure that water and sanitary connection to the building is sequenced within the project schedule to avoid potential critical path delays:
- Coordinate with owner and utility provider to ensure required water and sewer accounts are set up and fees are paid (tap, sewer impact, etc).
- Superintendent shall coordinate with local jurisdiction having authority (AHJ) to clearly understand all jurisdictional requirements to release water/sewer. (Camera & testing, bacteria, etc)
- Plumbing fixtures topped out and inspections passed.