POLICY: Subcontractor’s Daily Report
PURPOSE: To record each subcontractor’s daily work activities and manpower.
RESPONSIBILITY: The Superintendent
PROCEDURE:
1. Each subcontractor will be issued a block of Subcontractor’s Daily Reports before he begins work.
2. The subcontractor will complete the Daily Report and submit it to the field office not later than 8:30 AM for the previous day’s work.
3. This report will be used to compile the information for the project’s Daily Report and will be considered an extension of it.
4. The Subcontractor’s Daily Report will be attached to the Superintendent’s Daily Report and submitted to the Director of Field Operations weekly (end of the day Friday).